A redundant fuel storage pond containing a wide variety of radioactive residues was to be decommissioned

The facility was constructed approximately 50 years ago and the building infrastructure was limited. The material stored within the facility had to be removed and transferred to modern facilities for processing and ultimate storage.

The Issues

The data available to support development of a definitive solution for waste recovery and export was limited. This meant that a strategy had to be developed that was flexible enough to accommodate uncertainties.

The solution also had to marry with new facilities operating to modern standards which placed a high demand upon the limited infrastructure. The strategy also had to be consistent with the site wide strategy for dealing with waste material similar to the types stored in the pond.

Our role was to work with the project to assist the development of an appropriate strategy for decommissioning the pond. 

Our Solution >>