Our Solution
We established a definition of the waste streams and the degree of
uncertainty relating to each with respect to the key parameters for
disposal was also identified.
Solutions were then developed for
each waste stream that addressed the constraints imposed by the limited
facility infrastructure and those imposed by modern facilities and the
site wide strategy. The strategy was then subject to an overview risk
assessment to define key assumptions and areas of uncertainty.
A
programme of work was developed to resolve areas of uncertainty and
provide a robust solution for the decommissioning of the pond. Specific
studies were carried out to develop solutions for aspects of the
strategy.